top of page
CONSTRUCTION WORK IN SUMMER:
can lead to increased noise and partially restrict the view of the Matterhorn, further information -->
CONSTRUCTION WILL TAKE PLACE IN SUMMER
Please note that construction work is taking place in front of and partially inside the hotel this summer. This construction work may result in increased noise on weekdays from 7:30 a.m. to 6:00 p.m. (Saturday and Sunday are closed). In addition, a construction crane may slightly obstruct the view of the Matterhorn from the Matterhorn-view rooms. Matterhorn-view rooms will continue to have a view of the Matterhorn. We will endeavor to keep you informed about the progress of the work.
Since the new building is being constructed by our neighbors, we are unfortunately not always able to tell you exactly how the construction work will progress over the course of the summer.
If you have any questions, we are happy to help.
info@capricorn-zermatt.ch
during summer
New building in front of hotel: If everything runs according to schedule, the outer building facade will be built in the summer.
12.05.- 30.06.2025
Room renovations: We are renovating three bathrooms. The main work took place in the off-season. Therefore, the work involving noise is mostly short-term and only rare.
28.04. - 23.05.2025
New building in front of the hotel: It is excavation time, at the same time the geothermal probes are being completed.
24.04.2025
New building in front of hotel: Construction site installation and erection of the crane begins.
14.04.2025
New construction in front of the hotel: Drilling begins. The remaining geothermal probes are being installed.
07.04.2025
New building in front of hotel: The builder begins to erect the construction walls/fences, etc.